Secondary Clarifier (Circular) ​

Circular settling tank using Takács double-exponential settling model to separate mixed liquor into clarified effluent and thickened return activated sludge.

Overview ​

Secondary clarifiers (final settling tanks) perform two critical functions: clarification of the mixed liquor to produce low-TSS effluent, and thickening of biological sludge for return to the aeration basin or waste. They are the most critical unit operation in activated sludge treatment - poor clarifier performance can cause complete process failure regardless of biological treatment effectiveness.

When to Use ​

  • All activated sludge processes (conventional, extended aeration, MBR without membranes)
  • Following trickling filters or RBCs for biofilm separation
  • Nutrient removal systems (require proper RAS/WAS control)
  • Small to large plants (0.1-100+ MLD)

Key Characteristics ​

  • Dual function: clarification + thickening
  • Sensitive to sludge settling characteristics (SVI)
  • Requires continuous monitoring and control
  • Critical for process stability
  • Sludge blanket management essential
  • Denitrification can occur in blanket (nutrient removal systems)

Operating Modes ​

Basic Mode ​

  • Fixed overflow rate based on SVI
  • Simplified effluent TSS calculation
  • Default RAS/WAS split
  • Basic solids balance

Advanced Mode ​

  • 1D layer model (10 layers) with dynamic mass balance
  • Takács double-exponential settling velocity model
  • State point analysis for flux theory
  • Sludge blanket tracking
  • Denitrification in blanket (anoxic conditions)
  • Effluent quality prediction based on loading

Mathematical Model ​

Governing Equation - Takács Settling Velocity ​

The Takács model describes activated sludge settling as a function of concentration:

$$V_s = V_0 \times (e^{-r_h \times (X - X_{min})} - e^{-r_p \times (X - X_{min})})$$

Where:

  • $V_s$ = settling velocity (m/d)
  • $V_0$ = maximum theoretical settling velocity (m/d), typically 474 m/d
  • $r_h$ = hindered settling parameter (m³/g), typically 0.000576 m³/g
  • $r_p$ = flocculant settling parameter (m³/g), typically 0.00286 m³/g
  • $X$ = MLSS concentration (g/m³)
  • $X_{min}$ = non-settleable fraction (g/m³), typically 0

Model Behavior:

  • At low concentrations (X → 0): Dominated by first exponential (discrete settling)
  • At high concentrations (X → Xmax): Dominated by second exponential (hindered settling)
  • Produces characteristic parabolic settling velocity curve

Solids Flux Theory ​

Total solids flux is the sum of gravity flux and underflow flux:

$$G_{total} = G_{gravity} + G_{underflow}$$

$$G_{gravity} = V_s(X) \times X$$

$$G_{underflow} = \frac{Q_u}{A} \times X$$

Where:

  • $G$ = solids flux (kg/m²·d)
  • $Q_u$ = underflow rate (m³/d)
  • $A$ = clarifier surface area (m²)

State Point Analysis ​

The state point defines the operating condition:

$$G_{applied} = \frac{Q_{in} \times X_{in}}{A}$$

The limiting flux $G_L$ is found from the flux curve:

$$G_L = \min(G_{total}) \text{ for } X \in [0, X_{underflow}]$$

Design Criterion: $$G_{applied} < G_L$$

Otherwise, sludge blanket will rise and overflow.

1D Layer Model ​

The clarifier is divided into N layers (typically 10):

Mass Balance per Layer i: $$\frac{dX_i}{dt} = \frac{1}{A \times h_i} \times (Q_{i-1} \times X_{i-1} - Q_i \times X_i + V_s(X_{i+1}) \times A \times X_{i+1} - V_s(X_i) \times A \times X_i)$$

Where:

  • $h_i$ = layer height (m)
  • $Q_i$ = flow from layer i (m³/d)
  • Layer 0 = effluent (top)
  • Layer 9 = underflow (bottom)

Effluent TSS Prediction ​

Empirical correlation based on overflow rate and sludge properties:

$$TSS_{eff} = TSS_{min} + k_{esc} \times \left(\frac{SOR}{SOR_{design}}\right)^{1.5} \times \left(\frac{SVI}{SVI_{design}}\right)^{0.8}$$

Where:

  • $TSS_{min}$ = minimum achievable TSS (5-10 mg/L)
  • $k_{esc}$ = solids escape coefficient (empirical)
  • $SOR$ = surface overflow rate (m³/m²·d)
  • $SVI$ = sludge volume index (mL/g)

Denitrification in Sludge Blanket ​

In nutrient removal systems, anoxic conditions develop in the sludge blanket:

$$r_{denit} = k_{denit} \times X \times \frac{NO_3}{K_{NO3} + NO_3} \times \frac{K_{O2}}{K_{O2} + DO}$$

Where:

  • $r_{denit}$ = denitrification rate (mg N/L·h)
  • $k_{denit}$ = rate constant (0.1-0.3 mg N/g MLSS·h)
  • $K_{NO3}$ = half-saturation constant (0.5 mg/L)
  • $K_{O2}$ = oxygen inhibition constant (0.2 mg/L)

Rising Sludge:

Excessive denitrification produces N₂ bubbles that attach to flocs, causing rising sludge:

$$\text{Rising sludge risk if: } NO_3 > 5 \text{ mg/L and blanket depth} > 1.5 \text{m}$$

Design Parameters ​

Input Parameters ​

ParameterSymbolUnitRangeDefaultDescription
Tank diameter$D$m10-7030Circular tank diameter
Sidewater depth$H$m3-54.0Effective settling depth
Influent MLSS$X_{in}$mg/L2000-50003500Mixed liquor concentration
Influent flow$Q_{in}$m³/d--Flow from aeration basin
RAS flow$Q_{RAS}$m³/d--Return activated sludge flow
Target RAS conc$X_{RAS}$mg/L8000-1200010000Underflow concentration
SVI-mL/g80-200120Sludge volume index
V0 (Takács)-m/d200-800474Max settling velocity
rh (Takács)-m³/g0.0003-0.0010.000576Hindered parameter
rp (Takács)-m³/g0.001-0.0050.00286Flocculant parameter

Output Parameters ​

ParameterUnitDescription
Surface aream²Required clarifier area
SORm³/m²·dSurface overflow rate
Solids loadingkg/m²·dSolids loading rate
Effluent TSSmg/LPredicted effluent TSS
RAS flow requiredm³/dRequired RAS pumping
Blanket depthmSludge blanket level
State point fluxkg/m²·dApplied solids flux
Limiting fluxkg/m²·dMaximum sustainable flux

Configuration Guide ​

Step-by-Step Setup ​

  1. Determine Design Flows

    • Peak wet weather flow (PWWF)
    • Average flow
    • Return activated sludge (RAS) ratio
    • Typical RAS ratio: 0.5-1.5 × influent flow
  2. Characterize Sludge

    • Measure SVI (30-minute settling test)
    • Typical values:
      • Good settling: 80-120 mL/g
      • Moderate: 120-150 mL/g
      • Poor (bulking): >150 mL/g
    • Determine operating MLSS (design parameter from aeration basin)
  3. Select Surface Overflow Rate (SOR)

    Conservative design:

    SVI < 100: SOR = 20-25 m³/m²·d (average), 40-50 m³/m²·d (peak)
    SVI 100-150: SOR = 15-20 m³/m²·d (average), 30-40 m³/m²·d (peak)
    SVI > 150: SOR = 10-15 m³/m²·d (average), 20-30 m³/m²·d (peak)
  4. Calculate Required Area

    $$A = \frac{Q_{peak}}{SOR_{peak}}$$

    Example:

    Qavg = 10,000 m³/d
    Qpeak = 15,000 m³/d
    SVI = 120 mL/g
    SOR_peak = 35 m³/m²·d
    
    A = 15,000 / 35 = 428.6 m²
    D = √(4×A/π) = 23.4 m → Use 24m diameter (452 m²)
  5. Verify Solids Loading Rate

    $$SLR = \frac{Q \times X}{A}$$

    Typical limits:

    • Average: 100-150 kg/m²·d
    • Peak: 200-250 kg/m²·d
    SLR_avg = (10,000 × 3.5) / 452 = 77.4 kg/m²·d ✓
    SLR_peak = (15,000 × 3.5) / 452 = 116.2 kg/m²·d ✓
  6. State Point Analysis (Advanced)

    Calculate Takács settling velocity for range of concentrations:

    At X = 3,500 mg/L: Vs = 474 × (exp(-0.000576×3500) - exp(-0.00286×3500)) = 8.6 m/d
    G_gravity = 8.6 × 3.5 = 30.1 kg/m²·d
    
    For RAS rate Qu = 10,000 m³/d (R=1.0):
    G_underflow = (10,000/452) × 3.5 = 77.4 kg/m²·d
    
    G_total = 30.1 + 77.4 = 107.5 kg/m²·d
    G_applied = (10,000 × 3.5) / 452 = 77.4 kg/m²·d
    
    Safety factor = G_limiting / G_applied > 1.2 ✓
  7. Configure RAS/WAS Control

    • RAS pumping: Variable speed with blanket level control
    • Target blanket depth: 1.0-1.5 m (1/3 of sidewater depth)
    • WAS: Timer-based or flow-paced
    • Sludge age control: Adjust WAS to maintain target SRT

Typical Design Values ​

ApplicationSOR (avg)SOR (peak)SLR (avg)SLR (peak)DepthComments
Conventional AS (SVI 100)20-2540-50100-120180-2203.5-4.5Good settling
Extended aeration (SVI 120)16-2030-4080-100140-1804.0-4.5Moderate settling
Nitrification (SVI 100-120)16-2030-3580-100150-1804.0-5.0Avoid denitrification
BNR process (SVI 100-150)12-1624-3260-80120-1504.0-5.0Denitrification risk
Bulking sludge (SVI >150)10-1220-2450-70100-1204.5-5.0Poor settling

Performance Criteria ​

Achievable Effluent TSS ​

SVI (mL/g)MLSS (mg/L)SOR (m³/m²·d)Effluent TSS (mg/L)Performance
80-1002000-400015-205-10Excellent
100-1202500-400015-2010-15Good
120-1503000-450012-1615-25Moderate
150-1803000-500010-1225-40Poor (borderline bulking)
>180-<10>40Failing (bulking sludge)

RAS Concentration ​

Target RAS concentration depends on MLSS and RAS ratio:

$$X_{RAS} = X_{MLSS} \times (1 + \frac{1}{R})$$

MLSS (mg/L)RAS Ratio (R)Target RAS (mg/L)Achievable with SVI
20001.0400080-150
30000.75525080-130
35001.0700080-120
40001.0800080-110
50000.5750080-100

Denitrification in Clarifier ​

Conditions favoring denitrification:

  • High nitrate in MLSS (>5 mg/L)
  • Deep sludge blanket (>1.5 m)
  • High temperature (>15°C)
  • Long blanket retention time

Consequences:

  • Rising sludge (nitrogen gas bubbles)
  • Poor effluent quality
  • Loss of nitrate removal credit
  • Phosphorus release (if anaerobic)

Mitigation:

  • Increase RAS pumping rate (reduce blanket depth)
  • Reduce nitrate recycling to anoxic zone
  • Pre-anoxic zone to consume nitrate
  • Shorter clarifier detention time

Troubleshooting ​

IssueCauseSolution
High effluent TSSHydraulic overload (high SOR)Reduce flow, add clarifiers, increase area
Solids overload (high SLR)Reduce MLSS, waste more sludge
Bulking sludge (high SVI)Address bulking cause (see below)
Rising sludge blanketIncrease RAS rate, reduce blanket depth
Density currentsCheck for temperature stratification, add baffles
Rising sludge (denitrification)High nitrate + deep blanketIncrease RAS rate, reduce nitrate to clarifier
Septicity in blanketIncrease WAS, reduce blanket retention
Low RAS concentrationPoor settling (high SVI)Address bulking, reduce SRT
High RAS rateReduce RAS pumping if possible
Short-circuitingCheck feed distribution, improve mixing
Blanket loss to effluentRAS pump failureRepair pump immediately, emergency shutdown
Sudden flow surgeInstall flow equalization
Scum/foam carryoverInstall scum baffles, check for surfactants
Filamentous bulking (SVI >150)Low F/M ratioIncrease F/M, reduce SRT or aeration basin volume
Nutrient deficiencyAdd nitrogen or phosphorus
Low DOIncrease aeration
Septic conditionsEliminate dead zones, septage in primary
Viscous bulkingHigh EPS productionReduce SRT, check for shock loads
Pin flocVery low F/MIncrease F/M, reduce aeration volume
Over-aerationReduce DO setpoint

Operation & Maintenance ​

Daily Checks ​

  • Visual inspection of effluent clarity
  • Monitor blanket level (sludge judge or ultrasonic)
  • Verify RAS/WAS pumping rates
  • Check scum accumulation on surface
  • Observe density currents or short-circuiting
  • Record SVI (if daily sampling protocol)

Weekly Maintenance ​

  • 30-minute settleability test (SVI measurement)
  • Microscopic examination of sludge
  • Clean scum baffles and overflow weirs
  • Verify RAS/WAS flow meters
  • Check blanket level sensors
  • Inspect rotating mechanisms (scraper arms)

Monthly Tasks ​

  • Complete sludge profile (blanket mapping)
  • Calibrate level sensors
  • Measure RAS concentration
  • Review SVI trends
  • Check for signs of structural damage
  • Verify torque on rotating mechanisms
  • Review effluent TSS vs. design

Annual Tasks ​

  • Drain and inspect clarifier interior
  • Inspect and repair scraper mechanisms
  • Clean weirs and launders thoroughly
  • Repaint exposed surfaces
  • Structural inspection (concrete, welds)
  • Review performance vs. design (consider uprate if needed)
  • Update O&M procedures

Advanced Features ​

Dynamic Blanket Control ​

Modern clarifiers use ultrasonic or pressure sensors for real-time blanket level control:

$$Q_{RAS} = Q_{RAS,base} + K_p \times (h_{blanket} - h_{setpoint})$$

Where:

  • $Q_{RAS,base}$ = baseline RAS flow (flow-paced)
  • $K_p$ = proportional gain
  • $h_{blanket}$ = measured blanket level (m)
  • $h_{setpoint}$ = target blanket depth (typically 1.0-1.5 m)

Control Objectives:

  • Maintain stable blanket depth
  • Prevent blanket loss
  • Maximize RAS concentration
  • Minimize denitrification in blanket

Solids Flux Analysis ​

Plotting gravity flux vs. underflow flux identifies operating constraints:

For X from 0 to X_max:
  Vs = Takács_model(X)
  G_gravity = Vs × X
  G_underflow = Qu/A × X
  G_total = G_gravity + G_underflow

Plot G_total vs X:
  Minimum = Limiting flux (design constraint)
  At X_min = Critical concentration

Design margin:

  • Applied flux should be <80% of limiting flux for safety

Temperature Effects ​

Temperature affects settling primarily through viscosity:

$$V_s(T) = V_s(20°C) \times \frac{\mu(20°C)}{\mu(T)}$$

$$\mu(T) = \mu(20°C) \times 1.002^{(20-T)}$$

Impact:

  • Cold weather (5°C): ~40% reduction in settling velocity
  • Warm weather (25°C): ~10% improvement
  • Design for worst-case (winter) conditions

Storm Flow Management ​

During wet weather:

  • SOR increases dramatically
  • Dilution of MLSS (if combined system)
  • Risk of blanket loss

Strategies:

  • Flow equalization upstream
  • Storm tanks to dampen peaks
  • Temporary acceptance of higher effluent TSS
  • Emergency return of storm flow to head of plant

Worked Example ​

Given ​

  • WWTP design: 15,000 m³/d (average), 22,500 m³/d (peak wet weather)
  • Aeration basin MLSS: 3,500 mg/L
  • SVI: 120 mL/g (design), measured: 110 mL/g
  • Desired SRT: 10 days
  • Aeration basin volume: 5,000 m³

Solution ​

Step 1: Select Design SOR

For SVI = 120 mL/g:
SOR_avg = 18 m³/m²·d
SOR_peak = 32 m³/m²·d (conservative)

Step 2: Calculate Required Area

A = Q_peak / SOR_peak = 22,500 / 32 = 703.1 m²
D = √(4×703.1/π) = 29.9 m → Use two 24m diameter clarifiers
A_actual = 2 × π × 12² = 904.8 m²

Step 3: Verify Average Conditions

SOR_avg = 15,000 / 904.8 = 16.6 m³/m²·d ✓ (within 18 limit)

Step 4: Calculate Solids Loading

SLR_avg = (15,000 × 3.5) / 904.8 = 58.1 kg/m²·d ✓ (target <100)
SLR_peak = (22,500 × 3.5) / 904.8 = 87.0 kg/m²·d ✓ (target <150)

Step 5: Determine RAS Flow

For MLSS balance and RAS concentration of 10,000 mg/L:
R = X_MLSS / (X_RAS - X_MLSS) = 3,500 / (10,000 - 3,500) = 0.538
Q_RAS = 0.538 × 15,000 = 8,070 m³/d (average)

Check if achievable with SVI=120:
Stirred SVI test: 1000 mL @ 3500 mg/L settles to 420 mL in 30 min
SVI = 420/3.5 = 120 mL/g ✓
Expected RAS concentration ≈ 1000/100 mL × 1000 = 10,000 mg/L ✓

Step 6: Takács State Point Analysis

Takács parameters (default):
V0 = 474 m/d
rh = 0.000576 m³/g
rp = 0.00286 m³/g

At X = 3,500 mg/L:
Vs = 474 × (exp(-0.000576×3500) - exp(-0.00286×3500))
   = 474 × (0.1184 - 0.0001)
   = 56.1 m/d = 2.34 m/h

G_gravity = 56.1 × 3.5 = 196.4 kg/m²·d
G_underflow (avg) = (8,070/904.8) × 3.5 = 31.2 kg/m²·d
G_applied = 58.1 kg/m²·d

Limiting flux analysis shows G_L ≈ 150 kg/m²·d (occurs at X ≈ 6500 mg/L)
Safety factor = 150 / 58.1 = 2.58 ✓ (good margin)

Step 7: WAS for SRT Control

SRT = (V × X) / (Qw × Xw + Qe × Xe)

Assuming Qw × Xw >> Qe × Xe:
Qw = (V × X) / (SRT × X_RAS)
   = (5,000 × 3.5) / (10 × 10)
   = 175 m³/d

Sludge production check:
Px ≈ 0.4 kg TSS/kg BOD removed (typical for AS)
BOD removal = 15,000 × 0.250 = 3,750 kg/d (assuming 250 mg/L)
Px = 0.4 × 3,750 = 1,500 kg/d
WAS mass = 175 × 10 = 1,750 kg/d (reasonable match)

Step 8: Effluent TSS Prediction

At SVI = 110, SOR = 16.6 m³/m²·d, MLSS = 3500 mg/L:
TSS_eff ≈ 8 + 0.05 × (SOR - 15) = 8 + 0.08 = 8.1 mg/L (excellent)

At peak: SOR = 24.9 m³/m²·d:
TSS_eff ≈ 8 + 0.05 × (24.9 - 15) = 8 + 0.5 = 8.5 mg/L (still good)

Summary ​

  • Two 24m diameter clarifiers (904.8 m² total)
  • Depth: 4.5 m (sidewater depth)
  • RAS pumping: 8,070 m³/d (average) with VFD control
  • WAS: 175 m³/d for SRT = 10 days
  • Expected performance: <10 mg/L TSS effluent

References ​

  1. Takács, I., Patry, G.G., and Nolasco, D. (1991). "A Dynamic Model of the Clarification-Thickening Process." Water Research 25(10): 1263-1271.
  2. WEF (2018). Design of Municipal Wastewater Treatment Plants, MOP 8, 6th Ed., Ch. 13.
  3. Metcalf & Eddy (2014). Wastewater Engineering: Treatment and Resource Recovery, 5th Ed., pp. 988-1045.
  4. Ekama, G.A., Barnard, J.L., Günthert, F.W., et al. (1997). Secondary Settling Tanks: Theory, Modelling, Design and Operation. IAWQ Scientific and Technical Report No. 6.
  5. ATV-DVWK (2000). Dimensioning of Single-Stage Activated Sludge Plants, ATV-A 131E.
  6. Parker, D.S., Kaufman, W.J., and Jenkins, D. (1972). "Floc Breakup in Turbulent Flocculation Processes." J. San. Eng. Div., ASCE 98(SA1): 79-99.
  7. UK Water Industry Research (2013). Activated Sludge Modelling for Design and Operation.