Screens
Physical removal of large objects and debris from raw wastewater
Overview
Screens are the first treatment unit in WWTPs, removing large solids (rags, wood, plastics, grit) that could damage pumps or clog downstream processes. Types include bar screens (coarse, 25-50mm), fine screens (3-10mm), and micro-screens (<1mm). Screenings are typically 5-40 L/ML treated, requiring compaction and disposal.
Theory and Equations
Basic Mode
$$Q_{screenings} = Q \times f_{screen}$$
Where:
- Q = flow rate (ML/d)
- f_screen = specific screenings production (L/ML)
- Coarse bar screens: 5-15 L/ML
- Fine screens: 10-30 L/ML
- Micro-screens: 20-40 L/ML
Advanced Mode
Headloss Through Clean Screen:
$$h_L = \frac{v^2}{2g} \times C \times \left(\frac{w}{b}\right)^{4/3} \times \sin\theta$$
Where:
- v = approach velocity (m/s)
- C = bar shape coefficient (2.42 sharp, 1.79 round, 1.67 teardrop)
- w = bar width (m)
- b = clear spacing (m)
- θ = screen angle from horizontal
Headloss with Clogging:
$$h_L = h_{L,clean} \times (1 + f_{clog})$$
Where f_clog = 1.5-3.0 (50-200% increase)
Model Parameters
| Parameter | Coarse Bar | Fine Screen | Micro-Screen | Units |
|---|---|---|---|---|
| Bar/Opening Size | 25-50 | 3-10 | 0.5-3 | mm |
| Approach Velocity | 0.6-1.2 | 0.6-0.9 | 0.3-0.6 | m/s |
| Through Velocity | <1.0 | <1.2 | <0.8 | m/s |
| Headloss (clean) | 150-300 | 200-400 | 300-600 | mm |
| Screenings | 5-15 | 10-30 | 20-40 | L/ML |
Design Criteria
| Type | Clear Opening | Application | Cleaning |
|---|---|---|---|
| Coarse Bar | 25-50 mm | Preliminary | Manual/mechanical |
| Medium Bar | 10-25 mm | Preliminary | Mechanical |
| Fine Screen | 3-10 mm | Primary bypass | Mechanical |
| Micro-Screen | 0.5-3 mm | Enhanced primary | Continuous |
Worked Example
Given: Fine screen design
- Peak flow: 500 L/s
- Bar width: 10 mm
- Clear spacing: 6 mm
- Screen angle: 60° from horizontal
Calculate: Number of bars and headloss
- Approach area (assume 1.2m wide × 1.0m deep): 1.2 m²
- Approach velocity: 0.5 / 1.2 = 0.42 m/s
- Headloss: Use equation with C = 2.42, calculate ~250mm
- Number of clear spaces: 1.2m / 0.016m = 75 openings
References
- Metcalf & Eddy (2014). Wastewater Engineering, 5th Edition
- WEF (2018). Design of Water Resource Recovery Facilities, MOP 8