Grease Trap ​

Gravity separation device for removing fats, oils, and grease (FOG) from wastewater through buoyancy-driven separation.

Overview ​

Grease traps (also called grease interceptors) use the density difference between water and FOG to achieve separation. As wastewater flows through the device at low velocity, lighter FOG floats to the surface where it is retained, while heavier solids settle to the bottom. Clarified water exits through a submerged outlet.

When to Use ​

  • Food service establishments (restaurants, kitchens)
  • Food processing facilities
  • Industrial sites with FOG in wastewater
  • Municipal WWTPs with high FOG influent
  • Upstream of biological treatment (protects biomass)
  • Before sewer discharge (prevent blockages)

Key Characteristics ​

  • Simple gravity separation (no power required)
  • Removes >90% of free FOG
  • Requires regular pumping/cleaning
  • Can cause odor if poorly maintained
  • May need heating in cold climates

Operating Modes ​

Basic Mode ​

  • Fixed FOG removal efficiency (default 90%)
  • Simplified detention time
  • Constant temperature

Advanced Mode ​

  • Stokes' Law for grease particle rise
  • Temperature-dependent viscosity
  • Emulsified vs. free oil modeling
  • Solids settling concurrent with FOG rise

Mathematical Model ​

Governing Equation - Stokes' Rising Velocity ​

$$V_r = \frac{g \times d^2 \times (\rho_w - \rho_f)}{18 \mu}$$

Where:

  • $V_r$ = terminal rise velocity (m/s)
  • $g$ = gravitational acceleration (9.81 m/s²)
  • $d$ = droplet diameter (m)
  • $\rho_w$ = water density (1000 kg/m³)
  • $\rho_f$ = FOG density (kg/m³, typically 900-950)
  • $\mu$ = dynamic viscosity (Pa·s)

Typical FOG Properties ​

PropertyValue
Density900-950 kg/m³
Specific gravity0.90-0.95
Viscosity @ 20°C0.03-0.08 Pa·s (30-80 cP)
Viscosity @ 40°C0.01-0.03 Pa·s (10-30 cP)

Detention Time ​

$$t = \frac{H}{V_r}$$

Where:

  • $t$ = minimum detention time (s)
  • $H$ = effective water depth (m)

For droplet d = 0.15mm (150 µm) at 20°C:

  • V_r ≈ 0.0002-0.0004 m/s (varies with oil type)
  • For H = 1.0m: t = 2500-5000s (40-85 min)

Required Volume ​

$$V = Q \times t$$

Where:

  • $V$ = trap volume (m³)
  • $Q$ = flow rate (m³/s)
  • $t$ = detention time (s)

Surface Area Requirement ​

$$A = \frac{Q}{V_r}$$

Where:

  • $A$ = surface area (m²)
  • Critical for FOG to reach surface

Design Parameters ​

Input Parameters ​

ParameterSymbolUnitRangeDefaultDescription
Flow rateQL/s0.1-505Design flow
Detention timetmin10-6030At design flow
Water depthHm0.5-2.01.0Effective depth
TemperatureT°C10-4020Wastewater temperature
FOG concentrationC_FOGmg/L50-2000300Inlet FOG
Target droplet sizedmm0.10-0.250.15Design particle

Output Parameters ​

ParameterUnitDescription
FOG removal%Free FOG captured
Trap volumeL or m³Total capacity
FOG storageLAccumulated FOG layer
Solids storageLSettled solids capacity
Cleaning frequencydaysRecommended pumping interval

Configuration Guide ​

Step-by-Step Setup ​

  1. Estimate Peak Flow Rate

    • Restaurants: 0.05-0.15 L/s per seat
    • Commercial kitchens: 0.1-0.3 L/s per fixture
    • Food processing: Measure or estimate
  2. Select Detention Time

    • Minimum: 10 minutes (small traps, pre-treatment)
    • Standard: 20-30 minutes (most applications)
    • High efficiency: 40-60 minutes (heavy FOG loads)
  3. Calculate Required Volume $$V = Q \times t \times 60$$

    Example: Q = 5 L/s, t = 30 min V = 5 × 30 × 60 = 9,000 L = 9 m³

  4. Determine Dimensions

    • Length-to-width ratio: 2:1 to 4:1 (reduces short-circuiting)
    • Depth: 1.0-1.5m typical
    • Surface area: Critical for FOG rise
  5. Configure Inlet/Outlet

    • Inlet: Submerged, with baffle to reduce turbulence
    • Outlet: Submerged, with tee or baffle to retain FOG
    • Inlet-to-outlet distance: >2/3 of length
  6. Add Baffles

    • Inlet baffle: Distribute flow, prevent jetting
    • Outlet baffle: Prevent FOG escape
    • Internal baffles: Improve plug flow (optional)
  7. Plan Maintenance Access

    • Manhole(s) for pumping access
    • Sampling ports
    • Ventilation

Typical Design Values ​

ApplicationFlow (L/s)Detention (min)Volume (L)Frequency (weeks)
Small restaurant (50 seats)2.5-5203,000-6,0004-8
Large restaurant (200 seats)10-203018,000-36,0002-4
Commercial kitchen5-15257,500-22,5004-6
Food processing (small)10-304024,000-72,0001-2

Regulatory Requirements ​

UK/EU:

  • EN 1825: Grease separators standard
  • Minimum 200L volume (very small installations)
  • Required where FOG >50 mg/L to sewer

USA:

  • PDI G101: Grease interceptor sizing standard
  • Varies by jurisdiction (1-3× flow per minute common)
  • Some cities require traps >3,000 gallons (11,000L)

Performance Criteria ​

Removal Efficiency ​

FOG TypeRemoval Efficiency
Free floating oil/grease85-95%
Coalesced droplets (>150µm)80-90%
Fine emulsion (<50µm)10-30%
Solidified fats (cold)90-99%

Note: Grease traps remove free/floatable FOG, NOT emulsified or dissolved FOG.

Factors Affecting Performance ​

FactorEffect on Efficiency
Low temperatureReduces (FOG solidifies, higher viscosity)
High flow/turbulenceReduces (re-entrainment, short-circuiting)
Detergents/surfactantsGreatly reduces (emulsifies FOG)
Long detentionImproves (more rise time)
Regular cleaningImproves (maintains volume)

UK Design Standards ​

ParameterValueStandard
Minimum detention10 minEN 1825
Typical detention20-40 minBuilding regulations
Depth0.8-1.5mEN 1825
FOG layer alarm25% of depthGood practice
Cleaning frequencyFOG+solids <50% volumeEN 1825

Types of Grease Traps ​

Passive Gravity (This Unit) ​

Configuration:

  • Underground tank
  • Inlet and outlet pipes
  • Baffles for flow distribution
  • No power required

Advantages:

  • Simple, reliable
  • No operating cost
  • Long service life

Disadvantages:

  • Large size requirement
  • Regular pumping needed
  • Odor potential

Small Under-Sink Traps ​

Configuration:

  • Compact (20-200L)
  • Installed under fixtures
  • Easy access for cleaning

Use:

  • Small cafes, bars
  • Individual fixtures
  • Supplemental to main trap

Limitations:

  • Frequent cleaning (weekly)
  • Lower efficiency
  • Not suitable as primary treatment

Automatic Grease Recovery Units (AGRU) ​

Configuration:

  • Mechanical skimming
  • Heated surfaces
  • Automated FOG removal

Advantages:

  • Continuous FOG removal
  • Smaller footprint
  • Less frequent service

Disadvantages:

  • Higher capital cost
  • Power requirement
  • Maintenance complexity

Troubleshooting ​

IssueCauseSolution
FOG in effluentTrap full (needs pumping)Pump out, increase frequency
High flow/turbulenceReduce flow or increase volume
Detergents emulsifying FOGEliminate detergent use, educate staff
Short-circuitingAdd/adjust baffles
Cold temperatureInsulate, add heating
Odor problemsAnaerobic conditionsPump more frequently
Solids accumulationFull cleanout (not just FOG layer)
Poor ventilationImprove venting
Long detentionReduce retention time slightly
Blockage/overflowFOG layer too thickEmergency pumping
Solids blocking outletFull cleanout, check outlet baffle
Structural failureInspect, repair/replace
Slow separationTemperature too lowHeat influent or trap
Emulsified FOGPrevent detergent use
TurbulenceImprove inlet design

Operation & Maintenance ​

Daily Checks (Staff) ​

  • Visual check for overflows
  • Observe inlet flow (no unusual color/odor)
  • Check for leaks

Weekly Checks ​

  • Measure FOG layer thickness (dipstick)
  • Check inlet/outlet for blockages
  • Verify ventilation

Monthly Maintenance ​

  • Detailed inspection via manhole
  • Measure solids layer
  • Check baffles and pipes
  • Review pumping records

Cleaning/Pumping ​

Indicators for Pumping:

  • FOG layer >25% of depth
  • FOG + solids layer >50% of depth (EN 1825)
  • Every 1-3 months typical for restaurants

Procedure:

  1. Pump out FOG layer
  2. Pump out water (middle layer)
  3. Remove settled solids
  4. Flush and clean interior
  5. Dispose of waste properly (licensed hauler)
  6. Refill with clean water

Important: Never use enzymes or biological additives without approval. These can emulsify FOG, causing pass-through to sewer and downstream problems.

FOG Disposal ​

Disposal Options ​

MethodRequirementsNotes
RenderingCollected FOG to rendererBest option, beneficial reuse (biodiesel)
Anaerobic digestionHigh-strength organicsCo-digest with biosolids
LandfillSolidified, mixed with absorbentLeast preferred
IncinerationEnergy recoveryOnly if no other option

Regulatory Compliance ​

UK:

  • Controlled waste (licensed carrier required)
  • Duty of care (waste transfer notes)
  • Waste hierarchy (prefer reuse/recovery)

Rendering/Biodiesel:

  • Clean FOG has value
  • Contamination reduces value
  • Regular collection preferred

Worked Example ​

Given ​

  • Restaurant: 120 seats
  • Operating hours: 12h/day (lunch & dinner)
  • Peak flow estimate: 0.10 L/s per seat
  • Design detention time: 30 minutes

Design ​

Step 1: Calculate Design Flow

$$Q = 120 \times 0.10 = 12 \text{ L/s}$$

Step 2: Determine Required Volume

$$V = Q \times t \times 60 = 12 \times 30 \times 60 = 21,600 \text{ L} = 21.6 \text{ m}^3$$

Round to V = 22 m³ (22,000L)

Step 3: Select Dimensions

Choose depth H = 1.5m Surface area A = V/H = 22/1.5 = 14.7 m²

For L:W = 3:1 rectangle:

  • L × W = 14.7
  • L = 3W
  • 3W² = 14.7 → W = 2.2m, L = 6.6m

Use: 6.5m long × 2.2m wide × 1.5m deep = 21.45 m³ ✓

Step 4: Estimate Cleaning Frequency

Assume:

  • FOG production: 50 g/seat/day
  • FOG density: 950 kg/m³

Daily FOG: 120 × 50 = 6,000 g = 6 kg/d Volume: 6/950 = 0.0063 m³/d = 6.3 L/d

FOG layer limit: 25% of 1.5m = 0.375m Volume available: 14.7 × 0.375 = 5.5 m³

Days to fill: 5,500/6.3 = 870 days (unrealistic)

More realistic with solids and safety factor:

  • Combined FOG + solids: ~20-30 L/d
  • Pump at 30% full (safety margin)
  • Frequency: (22,000 × 0.30)/25 = 264 days

Practical: Pump every 2-3 months (60-90 days) to prevent odor and ensure performance.

Step 5: Verify Rise Velocity

FOG droplet d = 0.15mm, SG = 0.92, T = 20°C, μ_w = 0.001 Pa·s

$$V_r = \frac{9.81 \times (0.00015)^2 \times (1000-920)}{18 \times 0.001} = 0.00098 \text{ m/s}$$

Time to rise H = 1.5m: $$t = 1.5/0.00098 = 1531 \text{ s} = 25.5 \text{ min}$$

Detention provided: 30 min ✓ (adequate)

Best Practices ​

Installation ​

  • Install as close to source as practical (shorter drains)
  • Provide easy access for pumping trucks
  • Ensure proper ventilation
  • Insulate in cold climates
  • Install FOG level alarm (optional but recommended)

Operation ​

  • Train kitchen staff on FOG prevention (scraping plates, dry wiping)
  • No food waste, paper, plastics into drains
  • No detergents or degreasers into trap
  • No hot water flushing (emulsifies FOG)

Maintenance ​

  • Regular pumping schedule (don't wait for blockage)
  • Full cleanout (not just FOG layer)
  • Inspect baffles and pipes
  • Keep records (regulatory requirement)

Advanced Features ​

Monitoring Systems ​

  • FOG level sensors (ultrasonic/capacitance)
  • Temperature monitoring
  • Flow meters
  • Alarms and telemetry

Enhancements ​

  • Heating coils (winter operation)
  • Automated sampling
  • Flow equalization
  • Pre-screening

References ​

  1. EN 1825-1 (2004). Grease Separators - Part 1: Principles of design, performance and testing.
  2. EN 1825-2 (2002). Grease Separators - Part 2: Selection of nominal size, installation, operation and maintenance.
  3. PDI G101 (2007). Grease Interceptors Standard. Plumbing & Drainage Institute.
  4. WEF (2008). Prevention and Control of Sewer System Overflows, 3rd Ed.
  5. Metcalf & Eddy (2014). Wastewater Engineering, 5th Ed.
  6. Water UK (2017). Sewers for Adoption, 8th Ed.