Overview
This section provides detailed design methodologies following UK water industry standards (PS208, PS211, PS221). Each calculation includes:
- Design equations with full derivations
- UK water industry standards and compliance criteria
- Worked examples with realistic values
- Parameter tables with acceptable ranges
- Related calculation dependencies
Design Calculation Topics
Primary Tanks
Primary sedimentation tank design per PS208 standards.
Key Parameters:
- Surface Overflow Rate: 1.0-1.2 m/h at DWF
- Retention time: 2-4 hours
- N-1 capacity requirements
- Sludge production estimates
Standards: UK PS208, UK operator guidelines
Biofilters
Trickling filter (biofilter) design per PS211 standards.
Key Parameters:
- BOD loading: 0.07 kgBOD/m³/d maximum
- Ammonia loading: 0.015 kgN/m³/d maximum
- Wetting rate: 0.04-0.75 m³/m²/h
- Recirculation requirements
Standards: UK PS211, biological treatment design
Humus Tanks
Secondary settling tank design per PS221 standards.
Key Parameters:
- Hydraulic loading: 1.0 m³/m²/h (all tanks), 2.0 m³/m²/h (N-1)
- Minimum HRT: 2 hours at maximum flow
- Minimum SWD: 2.0 m
- Humus sludge capture
Standards: UK PS221, UK operator design criteria
Chemical Dosing
Phosphorus removal using ferric sulphate with UK operator molar ratios.
Key Parameters:
- Fe:P molar ratios: 1.5-2.2 (typical 1.66)
- Dosing stages: primary, secondary, tertiary
- Storage requirements: 28 days supply
- Chemical sludge production
Standards: UK operator operational guidelines
Alkalinity Balance
Alkalinity consumption and supplementation for biological nutrient removal.
Key Parameters:
- Nitrification: 7.14 kg CaCO₃/kg NH₄-N
- Chemical dosing: 0.75 kg CaCO₃/kg Fe
- Minimum effluent alkalinity: 50 mg/L CaCO₃
- Sodium bicarbonate supplementation
Standards: Biological treatment chemistry
Sludge Production
Comprehensive sludge handling including production, thickening, and storage.
Key Parameters:
- Primary sludge: 40-60% SS removal
- Biological yield: 0.4-0.6 kgSS/kgBOD
- Storage: 14 days (UK operator), 4 days buffer
- Thickening targets: 3-6% DS
Standards: UK operator sludge management
Flow and Load
Hydraulic flow and pollutant load calculations for design basis.
Key Parameters:
- Population equivalent: 60g BOD/person/day (UK)
- DWF, 3DWF, 6DWF calculations
- Formula A (PS201) for FFT
- Diurnal flow factors
Standards: UK PS201, UK operator flow basis
Design Process Workflow
1. Flow and Load Basis
Start with Flow and Load calculations to establish:
- Design population (PE)
- Dry Weather Flow (DWF)
- Full Flow to Treatment (FFT via Formula A)
- Pollutant loads (BOD, SS, NH₄-N, TP)
2. Primary Treatment
Use Primary Tanks to design:
- Tank geometry (radial or rectangular)
- Verify PS208 compliance (upflow velocity, HRT)
- Check N-1 capacity
- Calculate primary sludge production
3. Biological Treatment
Design biofilters using Biofilters:
- Media volume based on BOD/NH₃ loading rates
- Recirculation requirements for wetting rate
- Temperature correction for efficiency
- Biomass production estimates
4. Secondary Settling
Size humus tanks per Humus Tanks:
- Surface area for hydraulic loading
- Verify PS221 compliance and N-1 capacity
- Humus sludge capture calculations
5. Phosphorus Removal (if required)
Apply Chemical Dosing:
- Determine dosing stage and Fe:P ratio
- Calculate chemical consumption
- Size storage tanks (28 days)
- Account for chemical sludge
6. Alkalinity Assessment
Check Alkalinity Balance:
- Calculate nitrification consumption
- Add chemical dosing consumption
- Verify effluent alkalinity ≥ 50 mg/L
- Size sodium bicarbonate dosing if needed
7. Sludge Management
Complete design with Sludge Production:
- Combine all sludge sources
- Calculate mixed sludge properties
- Design storage tanks (14 days UK operator)
- Assess liquor return impact
Key UK Standards Referenced
PS208 - Primary Sedimentation Tanks
- Maximum upflow velocity: 1.2 m/h (DWF), 2.0 m/h (FFT)
- Minimum retention time: 2 hours
- Minimum sidewater depth: 2.5 m
- N-1 compliance requirements
PS211 - Biological Filters
- Maximum BOD loading: 0.07 kgBOD/m³/d
- Maximum ammonia loading: 0.015 kgN/m³/d
- Wetting rate range: 0.04-0.75 m³/m²/h
PS221 - Humus Tanks
- Maximum HLR (all tanks): 1.0 m³/m²/h
- Maximum HLR (N-1): 2.0 m³/m²/h
- Minimum HRT: 2 hours
- Minimum SWD: 2.0 m
PS201 - Storm Flow Calculations
- Formula A: QFA = DWF + 1.36P + 3.18√P
- FFT determination
- Storm tank sizing
UK operator Operational Guidelines
- Fe:P molar ratios for phosphorus removal
- Sludge storage requirements (14 days)
- Alkalinity management criteria
Calculation Interdependencies
┌─────────────────┐
│ Flow and Load │ ← Start here: establish design basis
└────────┬────────┘
│
├──→ ┌─────────────────┐
│ │ Primary Tanks │ → Primary effluent quality
│ └────────┬────────┘
│ │
├──→ ┌───────▼─────────┐
│ │ Biofilters │ → Biomass production
│ └────────┬────────┘
│ │
├──→ ┌───────▼─────────┐
│ │ Humus Tanks │ → Humus sludge
│ └─────────────────┘
│
├──→ ┌─────────────────┐
│ │ Chemical Dosing │ → Chemical sludge, Fe dose
│ └────────┬────────┘
│ │
└──→ ┌───────▼─────────┐
│ Alkalinity │ → NaHCO₃ requirement
└─────────────────┘
│
┌───────▼─────────┐
│ Sludge Handling │ → Final storage design
└─────────────────┘Common Design Values (UK Practice)
Population Equivalent
- UK standard: 60g BOD/person/day
- EU standard: 54g BOD/person/day
- Per capita flow: 120-150 L/hd/d (domestic)
Diurnal Factors
- Peak flow factor: 1.5-2.5 × average
- Minimum flow factor: 0.33-0.50 × average
- FMEAN factor: 1.6 (UK operator standard)
Removal Efficiencies
- Primary tanks: 30-40% BOD, 50-60% SS
- Primary + chemical: 40% BOD, 60% SS, 70% TP
- Biofilters: 85% BOD, 85% NH₃
- Overall target: BOD ≤ 20 mg/L, SS ≤ 30 mg/L, NH₄-N ≤ 3 mg/L
Sludge Characteristics
- Primary sludge: 3-5% DS
- Humus sludge: 2% DS
- Mixed sludge: 2-4% DS (before thickening)
- Thickened sludge: 3-6% DS
Compliance Verification
When completing a design, verify compliance across all calculations:
Hydraulic compliance:
- Primary tanks: PS208 upflow velocities and HRT
- Biofilters: PS211 wetting rate range
- Humus tanks: PS221 hydraulic loading and HRT
Loading rate compliance:
- Biofilter BOD loading ≤ 0.07 kgBOD/m³/d
- Biofilter NH₃ loading ≤ 0.015 kgN/m³/d
N-1 redundancy:
- Primary tanks operable with one tank out
- Humus tanks operable with one tank out
- Blending tanks: minimum 2 for redundancy
Effluent quality targets:
- BOD ≤ 20 mg/L (or consent limit)
- SS ≤ 30 mg/L (or consent limit)
- NH₄-N ≤ 3 mg/L (or consent limit)
- TP ≤ 1 mg/L (if P removal required)
- Alkalinity ≥ 50 mg/L CaCO₃
Storage adequacy:
- Chemical storage: 28 days minimum
- Sludge storage: 14 days minimum (UK operator)
- Buffer tanks: 4 days typical
Related Documentation