SBR-Flexible - Flexible Cycle Sequencing Batch Reactor ​

Advanced SBR configuration with programmable cycle phases, adaptive timing, and automated control for optimal performance under varying load conditions.

Overview ​

The SBR-Flexible extends the standard SBR concept with programmable cycle phases, real-time optimization, and adaptive control strategies. This enables the reactor to respond dynamically to varying influent loads, achieve specific treatment targets, and handle storm events efficiently.

When to Use ​

  • Variable or unpredictable flow patterns
  • Seasonal load variations (tourism, industry)
  • Storm water handling requirements
  • Stringent nutrient limits requiring optimization
  • Plants requiring maximum operational flexibility

Key Characteristics ​

  • Fully programmable phase durations
  • Real-time cycle optimization
  • Multiple stored cycle profiles
  • Adaptive aeration control
  • Automated storm mode switching

Flexible Cycle Architecture ​

Standard Cycle Components ​

Fill Phase        React Phase       Settle   Decant   Idle
[Static/Mixed/   [Aerobic/Anoxic/  [No      [Effluent [Optional
 Aerated]         Alternating]      Mix]     Withdraw] Standby]

Programmable Sub-Phases ​

PhaseSub-PhasesVariables
FillStatic, Mixed, AeratedDuration, mixing intensity
ReactAerobic, Anoxic, AnaerobicDuration, DO target, sequences
SettleSingle phaseDuration, minimum depth
DecantVariable speedRate, end level, TSS trigger
IdleActive/PassiveWAS timing, next cycle prep

Phase Transition Triggers ​

Trigger TypeParameterApplication
Time-basedFixed durationStandard operation
Level-basedWater depthFill, Decant
Quality-basedNH4, NO3, PO4React optimization
Event-basedStorm signalEmergency mode

Control Strategies ​

Feed-Forward Control ​

Adjust cycle based on predicted load: $$Cycle_{adjusted} = Cycle_{base} \times \frac{Load_{predicted}}{Load_{design}}$$

Input signals:

  • Flow rate
  • Time of day
  • Day of week
  • Upstream conductivity

Feedback Control ​

Real-time optimization based on measured parameters:

Ammonia-Based Aeration Control (ABAC): $$t_{aerobic} = t_{aerobic,base} + K_p(NH_{4,target} - NH_{4,measured})$$

ORP-Based Phase Control:

  • Anoxic phase: ORP < -50 mV
  • Aerobic phase: ORP > +50 mV
  • Nitrate knee detection

Multi-Parameter Optimization ​

Optimize cycle for multiple objectives: $$J = w_1(NH_4 - NH_{4,target})^2 + w_2(NO_3 - NO_{3,target})^2 + w_3(Energy)$$

Advanced Phase Programming ​

BNR Cycle Example ​

PhaseDurationModeDOPurpose
Fill 120 minAnaerobic0P release
Fill 240 minAnoxic<0.3Denitrification
Fill 330 minAerobic2.0Start nitrification
React 160 minAerobic2.0BOD, nitrification
React 245 minAnoxic<0.3Post-denit
React 330 minAerobic2.0P uptake polish
Settle60 min--Clarification
Decant30 min--Effluent withdraw
Idle15 min--WAS, standby

Total: 5.5 hours

Storm Mode Cycle ​

PhaseDurationModeChanges
FillVariableAeratedExtended, high rate
React60 minAerobicShortened
Settle45 min-Shortened
Decant45 min-Extended, faster

Total: ~3 hours (increased throughput)

Weekend/Low-Load Cycle ​

PhaseDurationModeChanges
Fill120 minMixedExtended collection
React240 minVariableEnhanced treatment
Settle90 min-Extended settling
Decant45 min-Slow withdrawal

Total: 8+ hours (2-3 cycles/day)

Biokinetics Considerations ​

Batch Kinetics ​

Unlike continuous systems, SBR operates in batch mode:

$$\frac{dS}{dt} = -\frac{\mu_{max}}{Y} \times \frac{S}{K_s + S} \times X$$

Integrated form for substrate depletion: $$t = \frac{Y}{\mu_{max} X}\left[(S_0 - S) + K_s \ln\frac{S_0}{S}\right]$$

Variable MLSS Through Cycle ​

MLSS varies with fill volume: $$MLSS_{fill} = MLSS_{react} \times \frac{V_{react}}{V_{fill}} = MLSS_{react} \times \frac{1}{1-VER}$$

Where VER = Volume Exchange Ratio

Oxygen Demand Profile ​

OD varies significantly through react phase:

React TimeOD (relative)Dominant Process
0-30 min100%BOD oxidation
30-60 min70%BOD + nitrification
60-90 min50%Nitrification dominant
90-120 min30%Polishing

Design Equations ​

Flexible Volume Design ​

$$V_{total} = V_{min} + V_{fill} + V_{freeboard}$$

Where:

  • V_min = Minimum operating volume (sludge blanket)
  • V_fill = Maximum fill volume per cycle
  • V_freeboard = Storm surge capacity

Variable Cycle Capacity ​

$$Q_{daily} = V_{fill} \times n_{cycles} \times n_{basins}$$

With flexible cycles: $$Q_{max} = V_{fill} \times n_{max} \times n_{basins}$$

Decant Rate Calculation ​

$$Q_{decant} = \frac{V_{fill}}{t_{decant}}$$

Maximum rate limited by:

  • Weir overflow rate
  • Sludge blanket disturbance
  • TSS carryover

Parameters ​

Cycle Parameters ​

ParameterUnitDefaultRangeDescription
Base cycle timehours64-12Normal operation
Min cycle timehours32-4Storm mode
Max cycle timehours128-24Low-load mode
Fill phases-31-5Sub-phase count
React phases-31-6Sub-phase count
VER%2515-40Volume exchange

Control Parameters ​

ParameterUnitDefaultRangeDescription
NH4 targetmg/L20.5-5Aerobic endpoint
NO3 targetmg/L52-10Anoxic endpoint
DO setpointmg/L2.01.5-4.0Aerobic phase
ORP anoxicmV-100-200 to 0Anoxic indicator
Storm trigger-2xQ1.5-3xStorm mode entry

Decanter Parameters ​

ParameterUnitDefaultRangeDescription
Decanter type-floatingfixed/floatingWithdrawal device
Max ratem3/h500100-1500Withdrawal rate
Submergencem0.30.2-0.5Below surface
Min depthm2.52-4Sludge protection
TSS limitmg/L3010-50Quality cutoff

Configuration ​

Example Configuration ​

json
{
  "type": "sbrFlexible",
  "id": "sbr-basin-1",
  "parameters": {
    "volume": 3000,
    "minVolume": 1800,
    "depth": 5.5,
    "numberOfBasins": 3,
    "cycleProfiles": {
      "normal": {
        "totalTime": 6,
        "phases": [
          {"name": "fill-anaerobic", "duration": 0.5, "mode": "anaerobic", "fill": true},
          {"name": "fill-anoxic", "duration": 0.75, "mode": "anoxic", "fill": true},
          {"name": "fill-aerobic", "duration": 0.5, "mode": "aerobic", "fill": true, "do": 2.0},
          {"name": "react-aerobic", "duration": 1.5, "mode": "aerobic", "do": 2.0},
          {"name": "react-anoxic", "duration": 0.75, "mode": "anoxic"},
          {"name": "react-aerobic-polish", "duration": 0.5, "mode": "aerobic", "do": 1.5},
          {"name": "settle", "duration": 1.0},
          {"name": "decant", "duration": 0.5}
        ]
      },
      "storm": {
        "totalTime": 3,
        "phases": [
          {"name": "fill-aerated", "duration": 1.0, "mode": "aerobic", "fill": true, "do": 3.0},
          {"name": "react-aerobic", "duration": 0.75, "mode": "aerobic", "do": 3.0},
          {"name": "settle", "duration": 0.5},
          {"name": "decant", "duration": 0.75, "rate": "high"}
        ]
      },
      "lowLoad": {
        "totalTime": 8,
        "phases": [
          {"name": "fill-extended", "duration": 2.0, "mode": "mixed", "fill": true},
          {"name": "react-bnr", "duration": 4.0, "mode": "alternating", "aerobic": 0.6, "anoxic": 0.4},
          {"name": "settle", "duration": 1.5},
          {"name": "decant", "duration": 0.5}
        ]
      }
    },
    "control": {
      "cycleSelection": "automatic",
      "stormTrigger": 2.0,
      "lowLoadTrigger": 0.5,
      "abacEnabled": true,
      "nh4Target": 2.0,
      "no3Target": 5.0
    },
    "decanter": {
      "type": "floating",
      "maxRate": 400,
      "submergence": 0.3,
      "tssLimit": 25
    }
  }
}

Worked Example ​

Given ​

  • Design flow: 8,000 m3/d
  • Peak flow (storm): 20,000 m3/d
  • BOD: 180 mg/L, TN: 45 mg/L, TP: 8 mg/L
  • Targets: BOD <15, TN <8, TP <1 mg/L
  • 3 basins

Design ​

Step 1: Normal Operation

  • Cycles per day: 4 (6-hour cycles)
  • Fill volume per basin: 8,000 / (4 x 3) = 667 m3

Step 2: Basin Sizing (VER = 25%) $$V_{basin} = 667 / 0.25 = 2,668 \text{ m}^3$$

Round to 2,750 m3 per basin.

Step 3: Storm Mode Verification

  • Storm cycles: 8 (3-hour cycles)
  • Fill volume: 2,750 x 0.35 = 963 m3 (increased VER)
  • Capacity: 963 x 8 x 3 = 23,100 m3/d > 20,000

Step 4: Cycle Design

Normal BNR Cycle (6 hours):

PhaseDurationModeFillDO
Fill-Anaerobic30 minAnaYes0
Fill-Anoxic45 minAnoxYes<0.3
Fill-Aerobic30 minAerYes2.0
React-Aerobic90 minAerNo2.0
React-Anoxic45 minAnoxNo<0.3
React-Aerobic30 minAerNo1.5
Settle60 min-No-
Decant30 min-No-

Step 5: MLSS and SRT At MLSS = 4,500 mg/L: $$SRT = \frac{2,750 \times 4.5}{Q_w} \approx 18 \text{ days}$$

Step 6: Oxygen Demand Peak OD during aerobic phases:

  • BOD oxidation: 8,000 x 0.18 / 3 = 480 kg/d per basin
  • Nitrification: 8,000 x 0.045 x 4.6 / 3 = 552 kg/d per basin
  • Total: ~1,030 kg O2/d per basin

Step 7: Aeration System Peak rate during react-aerobic: $$SOTR = 1,030 / (0.6 \times 4/24) = 10,300 \text{ kg O}_2\text{/d equivalent}$$

Design for 1.5x safety: 15,500 kg/d capacity

Automation Features ​

Cycle Selection Logic ​

IF flow > storm_trigger THEN
    SELECT storm_cycle
ELSE IF flow < low_load_trigger THEN
    SELECT low_load_cycle
ELSE
    SELECT normal_cycle
END IF

Phase Termination Logic ​

AEROBIC PHASE:
    IF NH4 < target AND time > min_duration THEN
        GOTO next_phase
    ELSE IF time > max_duration THEN
        ALARM and GOTO next_phase
    END IF

ANOXIC PHASE:
    IF NO3 < target OR ORP < threshold THEN
        GOTO next_phase
    END IF

Troubleshooting ​

IssueCauseSolution
Incomplete nitrificationReact too shortExtend aerobic phase
Low DOIncrease aeration
Poor denitrificationNo anoxic timeAdd anoxic phase
Insufficient carbonEarlier anoxic or supplement
High effluent TSSShort settleExtend settle time
Fast decantReduce decant rate
Storm overflowCycle too longEnable storm mode
Floating sludgeDenit in settleMore pre-denit
Erratic performanceControl huntingTune PID parameters
  • SBR - Standard Sequencing Batch Reactor
  • CSTR - Continuously Stirred Tank Reactor
  • Granular-SBR - Granular Sludge SBR
  • BNR-Fundamentals
  • Process-Control

References ​

  1. Wilderer, P.A. et al. (2001). Sequencing Batch Reactor Technology. IWA Publishing.
  2. EPA (1999). Sequencing Batch Reactors. EPA/625/R-99/010.
  3. WEF (2018). Design of Municipal Wastewater Treatment Plants, MOP 8.
  4. Olsson, G. & Newell, B. (1999). Wastewater Treatment Systems: Modelling, Diagnosis and Control. IWA Publishing.